Koidu Diamonds

Project Name: Koidu Diamonds

Client: BSG Resources

Location: Sierra Leone

Overview

Design and construction of a complete 1.2 Mtpa mine and kimberlite process plant in remote east Sierre Leone.  The process plant included:

Consulmet also designed and built all of the mine infrastructure, including the tailings storage facility, water and 10 MW power plant, mine workshops, explosive magazine, and the 800-person construction and permanent accommodation camps.

The complete project was constructed and commissioned in less than 12 months.

Process Plant

ROM bin and scrubbing circuit

ROM bin and scrubbing circuit

Crushing circuit

Crushing circuit

Surge bins and DMS modules

Surge bins and DMS modules

Coarse DMS and final recovery house

Coarse DMS and final recovery house

Water recovery circuit

Water recovery circuit

Coarse DMS module at night

Coarse DMS module

Non-Process Infrastructure

Mine heavy vehicle workshop (side)

Mine heavy vehicle workshop

Diesel yard

Diesel yard

Blasting bunker

Blasting bunker

Mine vehicle washdown bay

Mine vehicle washdown bay

Generator building

Generator building

Emulsion store

Emulsion store

Accommodation

Accommodation village

Accommodation village

Single-storey units

Single-storey units

Double-storey unit

Double-storey units

Entertainment buildings

Entertainment buildings

Mess hall - exterior

Mess hall - exterior

Mess hall - interior

Mess hall - interior

Kitchen

Kitchen